Ward 43 · Pune Municipal Corporation

Wanawadi - Kausar Baug

Corporator: TBD — Contact Sushaasan · Annual budget ₹2.7 Cr

Solution cost vs annual allocation₹6.7 L / ₹2.7 Cr(2%)

Resolving every active brief uses 2% of the ward's annual budget.

👥For Citizens

What's happening in this ward

3 issues reported this week
Water11 reports
4/5

Drain blockage on Wanawadi main road: backflow into residential basements after light rain.

Electricity14 reports
3/5

Streetlights out 6 days on Wanawadi-Salunke Vihar stretch; residents report night-safety concerns.

Traffic9 reports
3/5

Wanawadi-Bibwewadi link road peak congestion, school-bus + corporate-shuttle clash 8:45–9:15am.

📋For the Corporator's Office
AI-synthesised brief

Ready-to-act solution plan

Data-backed. Budget-checked. Steps named by department. The corporator's office decides — Sushaasan just does the groundwork.

Traffic✓ Within budget

Nine Reddit posts report peak-hour congestion on Wanawadi-Bibwewadi link road between 8:45-9:15am caused by school buses and corporate shuttles converging simultaneously. The bottleneck affects Ward 43 residents during morning commute with severity rated 3/5.

57
Priority
₹1.9 L estimate14 days5 steps
What government can do
  1. 1

    Deploy 2 traffic marshals at Wanawadi-Bibwewadi link road junction from 8:30-9:30am weekdays for 30 days to manually segregate school bus and shuttle traffic into designated lanes

    Traffic Engineering Cell3d₹1.3 L
  2. 2

    Re-time traffic signal at main Wanawadi-Bibwewadi junction to extend green phase by 15 seconds for link road approach during 8:30-9:30am slot

    Traffic Engineering Cell7d₹7K
  3. 3

    Paint dedicated school bus drop-off zone markings (50m length) on link road shoulder 200m before main junction to prevent buses stopping mid-road

    Roads Department10d₹12K
  4. 4

    Install 3 No Parking signboards with 8am-10am restriction on 150m stretch approaching junction on both sides

    Traffic Engineering Cell7d₹9K
  5. 5

    Repair and patch 40 sqm of damaged road surface at junction approach causing vehicle slowdown and lane-weaving

    Roads Department14d₹40K
How citizens can help

Respect new lane markings once they appear · RWA liaisons coordinate with Traffic Police rapid-response group · share specific evidence, not generalised complaints.

Citizens are partners, not petitioners.
Electricity✓ Within budget

14 Reddit posts report streetlights non-functional for 6 days on Wanawadi-Salunke Vihar stretch, with residents citing night-safety concerns. Average severity of 3.2/5 indicates moderate but persistent infrastructure failure requiring prompt restoration.

54
Priority
₹1.2 L estimate10 days6 steps
What government can do
  1. 1

    Deploy Street-Light Cell field technician to survey Wanawadi-Salunke Vihar stretch within 2 days; document exact pole numbers, fault type (cable cut/LED failure/panel damage), and GPS coordinates for all non-functional lights. Estimated 25-30 poles on this 1.8km stretch.

    Street-Light Cell2d₹0
  2. 2

    Procure 20 replacement LED fixtures (assuming 65% of reported outages are LED failures) at ₹3,500/pole from PMC-empanelled vendor; requisition through e-procurement portal with urgent delivery clause.

    Street-Light Cell4d₹70K
  3. 3

    Issue work order to PMC-contracted electrical maintenance agency for LED replacement and wiring repair at identified fault points; complete installation for all 20 poles at ₹1,200/pole labor cost.

    Street-Light Cell7d₹24K
  4. 4

    Replace 3 damaged feeder cables (estimated 150 metres total based on typical cluster failures) at ₹180/metre including trenching and laying by licensed electrical contractor.

    MSEDCL Coordination via Street-Light Cell7d₹27K
  5. 5

    Test all restored streetlights for 2 consecutive nights; junior engineer to submit photographic compliance report with timestamp and pole numbers to ward office.

    Street-Light Cell9d₹0
  6. 6

    Add Wanawadi-Salunke Vihar stretch (30 poles) to weekly preventive maintenance patrol route; update Street-Light Cell GIS database with new asset condition tags.

    Street-Light Cell10d₹0
How citizens can help

RWAs photo-log streetlight outages weekly · residents avoid junction-box tampering · use the MSEDCL fault-number helpline for evidence trail.

Citizens are partners, not petitioners.
Water✓ Within budget

11 Reddit reports document drain blockage on Wanawadi main road causing sewage backflow into residential basements after light rain. The issue indicates accumulated debris and inadequate drain capacity requiring immediate desilting and structural inspection.

64
Priority
₹3.5 L estimate21 days7 steps
What government can do
  1. 1

    Deploy drainage inspection team to survey Wanawadi main road storm drains from Kausar Baug junction to Wanawadi Chowk (approx 800m stretch) using CCTV camera inspection to map blockage points and structural damage within 3 days

    Drainage Department3d₹25K
  2. 2

    Execute mechanical desilting of identified blocked drain sections on Wanawadi main road using suction-cum-jetting machine, estimated 600 metres at ₹350/metre

    Drainage Department7d₹2.1 L
  3. 3

    Clear and rebuild 4 choked catch pits/gully chambers along affected stretch at ₹8000 per chamber including debris removal and masonry repair

    Drainage Department5d₹32K
  4. 4

    Install 6 new steel gratings with debris traps at drain inlets to prevent future blockage at ₹4500 per grating including installation

    Drainage Department4d₹27K
  5. 5

    Pump out accumulated backflow water from 3 most-affected residential basements using 2 portable dewatering pumps at ₹3000/day for 2 days

    Drainage Department2d₹12K
  6. 6

    Apply anti-septic treatment and disinfection spray in affected basement areas covering approximately 500 sqm at ₹40/sqm

    Health Department2d₹20K
  7. 7

    Repair damaged drain wall sections identified in inspection, estimated 15 running metres of masonry repair at ₹1800/metre

    Drainage Department6d₹27K