Erandwane heritage-area transformer aged — outage clusters reported every 3rd week.
Corporator: TBD — Contact Sushaasan · Annual budget ₹2.4 Cr
Resolving every active brief uses < 1% of the ward's annual budget.
Erandwane heritage-area transformer aged — outage clusters reported every 3rd week.
1 reports via instagram about water issues in this area (last 24h). Avg severity 2.0/5.
Data-backed. Budget-checked. Steps named by department. The corporator's office decides — Sushaasan just does the groundwork.
Residents report recurring power outages every 3 weeks in Erandwane heritage area due to an aged transformer, with 9 posts on Reddit documenting the issue. The transformer requires inspection and likely replacement or upgrade to restore reliable power supply.
Submit formal complaint letter to MSEDCL Pune Urban Circle office (Shivajinagar) requesting immediate inspection of the aged transformer serving Erandwane heritage area, citing 9 resident complaints and documented 3-week outage cycle
Deploy PMC electrical inspector to survey transformer location and document load patterns, connection count, and transformer nameplate capacity; prepare technical report with photographs
Install 4 LED streetlights with independent solar backup (₹4000/pole) at critical junctions near transformer zone to maintain minimum public lighting during outages
Escalate transformer replacement/upgrade request through corporator's office to MSEDCL Executive Engineer with PMC technical report attached; request timeline commitment in writing
Arrange 2 mobile DG sets (hired at ₹8000/day each) on standby for next anticipated outage cycle to power essential community facilities (water pumps, street lights) for up to 3 days
Publish SMS/WhatsApp alert to 500 registered ward residents with MSEDCL complaint number and expected resolution timeline using existing PMC ward communication system
RWAs photo-log streetlight outages weekly · residents avoid junction-box tampering · use the MSEDCL fault-number helpline for evidence trail.